PROJECT HIGHLIGHTS
CMC Steel Clean Air Baghouse Project
H&R completed a new baghouse project at CMC Birmingham in February 2017. The new baghouse is the largest in CMC Corporate Divisions spanning through the United States. H&R installed equipment for over a year working hand-in-hand with plant personnel scheduling … Read More
Southern Company Gorgas Overland Conveyor
In 2015 H&R installed 1-1/2 miles of overland conveyor system using crafty rigging over many obstacles and terrain. Conveyor stretched under ground and heights of over 100ft above ground. The fabricator closed shop and failed to provide materials and assistance. … Read More
CMC Steel Stacker Upgrade
H&R performed duties of replacing Danielle robotic stacker working with Italian engineers at CMC Steel Birmingham, Alabama. All parts and materials were brought in by removing roof using 375 ton crane while working totally in the blind and using … Read More